One of the most challenging contracts - expansion of 10x1.5 tubes

We rarely get called in for routine jobs; while we have previously handled relatively large tubes, this time we took on a task requiring precision craftsmanship: the hydraulic expansion of stainless steel tubes within the tube sheets of the E-901 first-stage distillation evaporator. The tube sheet thickness is 180 mm—a standard figure for us. However, the geometry is the real challenge: the tubes measure 10 x 1.50 mm. And believe me—in our line of work, size matters!

During hydraulic expansion, the ultra-high pressure acts not only on the tube but also subjects all mandrel components—and the mandrel itself—to immense loads; given the significant reduction in cross-sectional areas, such cyclic tensile stress rapidly leads to failures at the structure's most vulnerable points. While we anticipated high consumption of tooling and materials, the mandrels initially lasted only a fraction of their projected service life. After carefully analyzing the issue—specifically, that cracks were consistently appearing in one particular location—we identified the necessary design modifications and manufactured new mandrels that eliminated the defect. This approach succeeded, enabling us to meet our planned consumption targets. Fewer stoppages for retooling allowed us to complete the project on schedule and hand over the work to the client.

We now have this experience under our belts as well. Yes, we did incur some losses on the project, but we can state with a high degree of certainty that, as of today, we are the ONLY COMPANY IN THE WORLD to have performed hydraulic tube expansion of this size and scale. The skill level of our operators now rivals that of the specialists at HydroPro Inc. In any case, we are ready for the competition :)

It is worth noting that, despite currently using older Soviet-era hydraulic expansion equipment, the client views the prospect of purchasing a system tailored to their needs positively following our work. We may well return—as we did with a previous client—to carry out the commissioning of our machines.